Hours to finish a job when two work together

A batch of parts takes a master 12 hours to make alone, or an apprentice 18 hours alone. If the master works 3 hours first and then the two work together, how many more hours are needed to finish?

Answer
27/5 hours (5.4 hours)

Step-by-step

  1. 1/12 × 3 = 1/4
    Find the part of the job the master finishes first
  2. 1 - 1/4 = 3/4
    Find the part of the job still left to do
  3. 1/12 + 1/18 = 5/36
    Find how much the two finish together in one hour
  4. (3/4) ÷ (5/36) = 27/5
    Divide the work left by the combined hourly rate to get the time

Why it works

The master's 3 hours finish 1/4 of the job, the remaining 3/4 is done at a combined rate of 5/36 per hour, and 3/4 ÷ 5/36 = 27/5 hours.