Shared work: 10 days and 40 days alone

One worker alone can finish a job in 10 days, and another alone can finish the same job in 40 days. Working together, how many days do they need?

Answer
8 days

Step-by-step

  1. 1 ÷ 10 = 0.1
    Work done per day by A
  2. 1 ÷ 40 = 0.025
    Work done per day by B
  3. 1 ÷ (0.1 + 0.025) = 8
    Combined time = 1 ÷ combined rate

Why it works

Working together, the two work rates add: each rate is 1 divided by that person's own time, so the shared time is 1 divided by the sum of the two rates.

Common mistakes